2006 Pointe Estero Renovation Progress

November 24, 2006

Greetings from Fort Myers Beach!  I am pleased to inform you that your home away from home is now officially reopened!

Once again, the past month has seen tremendous production, with final punch work being completed on the sliding glass doors and windows as well as the balcony surfaces.  The screen enclosures were completed just weeks ago.

On the property exterior, we have completed the new landscaping around the perimeter of the building, replaced the wood decking on the bridge between the pool and the parking lot, and resurfaced and re-striped the driveway. 

Inside of the units, Housekeeping and Maintenance have completed the final cleans and preventative maintenance inspections and re-keyed the property to ensure that all master keys distributed during the shutdown have been cancelled.

I would like to remind everyone that our Annual Meeting is scheduled for Friday, December 8th at 12:30 p.m. with a cocktail party scheduled for the evening of Thursday, December 7th at 5:30 p.m.  I look forward to seeing you there!

Week of October 1 – October 7 

Greetings from Fort Myers Beach!  The past month has been very productive at Pointe Estero.  The balcony decks are now complete and look fantastic, and the painters are in the process of completing the caulking and touch up around the sliding glass doors.  The screen enclosures arrived early this week and are being staged in the parking lot.  We will begin the installation of the screens early next week following the completion of the painting and caulking and expect all of the enclosures to be installed by the end of October.   

Around the property, we have completed the addition of the paver walkway from the pool deck to the beach, and carpet in the elevator landings has been fully installed.  The landscaping around the building will begin by November 1st and the parking lot resurfacing will begin on November 13th.  The ground floor marble is scheduled to be cleaned and sealed on October 26th. 

Inside of the units, Housekeeping has completed the initial deep clean process and Maintenance is now in the process of testing all appliances and mechanical equipment.  Drapery installation is scheduled to begin on Monday October 9th, and is expected to be completed by October 30th.  At that point Housekeeping will begin their final cleanings.  Opening day is near, and we are all very excited at Pointe Estero!

Week of September 3 – September 10 

Last week was neither the productive nor sunny week that we’ve become used to this year, but thankfully, Tropical Storm Ernesto was just another rainmaker. 

With the threat of a tropical storm, turned hurricane, turned tropical storm, and a forecast to affect our area, we were faced with the responsibility of securing the on site equipment and protecting the building from potential damage.  Unfortunately, that meant a two day breakdown and securing process followed by a three day remobilization process.  In short, the rain delay resulted in a loss of approximately one week of production.  The good news is that we are once again operating at full speed with a series of Saturday work on the agenda in an attempt to get caught back up.  The contractors have begun to install the sealer on the patio decks on the 03 and 04 stacks, and the floor to ceiling windows for the ground, first and second floors have arrived and will be installed by the end of next week.  This week’s pictures include the sealer after it has been applied as well as some pictures of our neighbors at Caper Beach doing some concrete restoration work of their own.   

Housekeeping and Maintenance are now in the process of putting units back together and completing the initial deep cleans!  We are looking forward to November!

August 17, 2006 

Greetings from sunny Fort Myers Beach!  The past three weeks have continued to be productive as Tropical Storm Chris thankfully turned out to be no more than a slight inconvenience. 

I am pleased to announce that the unit and elevator landing windows have all been installed from the 16th floor down to the 1st, and all of the sliders from the 16th floor to the 2nd are also completed with the sliders on the 1st floor scheduled for completion this week.  The concrete on the balconies is in the process of being re-poured as the rebar replacement is finished, and we are scheduled to start applying the decorative topping by the first week of September. The landscaping project along Estero Boulevard has been completed and looks great!

 

Housekeeping is currently in the process of performing deep cleans in the kitchens and bathrooms, and the Maintenance department is performing preventative maintenance in all units such as cleaning out dryer vents, servicing the electronic door locks, painting, and overseeing the servicing of the air handlers.

On another note, I would like to inform everyone that our Annual Meeting is scheduled for Friday, December 8th at 12:30 p.m. with a cocktail party scheduled for the evening of Thursday, December 7th at 5:30 p.m.  I look forward to seeing you there and meeting most of you for the first time!

Weeks of July 9-July 23 

The weather has continued to cooperate with the Pointe Estero project and the past two weeks have seen some very positive production.  The windows at the elevator landings have been installed from the 16th floor down to the 5th floor and we are scheduled to have units completed from the 16th floor to the 9th by the second week of August, ready for inspection and deep clean.  The concrete restoration is 80% complete with all of the problem areas being identified and chipped out and we are in the process of repairing those areas and replacing the topcoat. 

The pavers around the pool on the pool deck are being replaced as we speak and the fountain has been drained, cleaned, and repainted and we have replaced all of the lights to give it a fresh look.  At our last Board of Directors meeting, the board approved a landscaping beautification project which entailed the replacement of the plantings along Estero Boulevard.  That project will be completed by the end of next week.  I will post pictures upon completion! 

Hope everyone has had a safe and enjoyable Summer!

Week of July 2-July 9 – Summary of Project

The concrete restoration project at Pointe Estero is in full swing and to date, without incident.  We are currently housing approximately 40 construction workers throughout 14 units.  The units are being cleaned three times weekly and inspected by management twice weekly.     

After setting up all of the material and platforms on the rooftop the contractors have repainted 50% of the building exterior, removed all of the balcony screens, frames, tile, and the top coat of concrete.  We are currently in the process of inspecting the rebar and chipping out the areas that need to be replaced.  Once that process is complete the concrete will be re-poured, top coat will be re-applied, the tile will be replaced with a quartz finish, and the reinstallation of the screens will begin.   

Unfortunately, the complete removal and replacement of the existing top coat was a process that we did not anticipate.  Only after the removal of the tile were we able to make the determination that this was necessary.  This will add two weeks to the schedule of the project; however it will not affect the scheduled opening date.  

Concurrent with the concrete restoration, we are also in the process of replacing all sliding glass doors and windows throughout the building.  This is happening from the top floor down and includes the addition of functioning windows and replacement of the carpet in all of the elevator landings. 

It’s truly an exciting time at Pointe Estero!

Weeks of June 18-July 2
With the return of the sunshine, we were able to get back to work on the week of June 18-25.  The staging of windows and doors on all of the floors as well as the demolition of the concrete topcoat on all of the balconies was the main focus.  We are now in installation mode of windows and doors working our way down from the 16th floor, with a second shipment due on Thursday June 29th.  The demolition of concrete topcoat should wrap up this week.  The pool project, which consisted of draining, acid washing and light replacement, will also be completed by the end of this week.

Week of June 11 - June 18
While Tropical Storm Alberto turned out to be just a rain maker for us in Southwest Florida, it did turn out to be more of an inconvenience for us at Pointe Estero. However, while we were not able to perform any exterior work on Monday, June 12th or Tuesday, June 13th, we were able to get ahead of schedule painting the elevator landings during those two days and the contractors will be working outside this weekend to make up the lost time. Windows and doors will arrive on property on Thursday, June 15th and installation will begin on Friday, June 16th.

Week of June 4-June 11
We are now in full concrete restoration mode as all of the screens and the aluminum frames have been completely removed from the balconies.  The process of removing the balcony tile will begin on Monday June 5, and will be completed by Friday June 9th.  The carpets from all of the elevator landings have been removed, and will be replaced toward the end of the project.  Next up…windows and doors!

Week of May 28-June 4
With the week of the shutdown upon us, we are in full project preparation mode.  We are cleaning all units, protecting interior contents, and taking inventory for both Housekeeping and Maintenance.  The contractors will be arriving throughout the week, with the removal of the screens and aluminum scheduled for Thursday and Friday this week.

Week of May 21-28
The upcoming Memorial Day long weekend kept us busy operationally, and the upcoming shutdown kept us busy with the project management.  We utilized this week to remove the hurricane shutters from the first and second floors and to prep the exterior landscaping by moving the landscaping and sprinklers three feet away from the building. 

Week of May 14-21
It’s not everyday that you get to have a 20 story crane in your driveway (thankfully), but on Tuesday May 16th, that’s exactly what we had at Pointe Estero as we staged the necessary construction equipment on the rooftops!  Things went without incident, and we reported zero guest complaints or issues. 

   